Status of Hydropower Projects
|
SN |
Project Name |
Location |
Developer |
Capacity (MW) |
Current Status |
|
1 |
Siuri Khola SHP |
Lamjung |
Nyadi Group |
5 |
Construction Complete; Connected to the National Grid, Commercial Operation started from 30th Asoj 2069 |
|
2 |
Lower Modi 1 |
Parbat |
United Modi |
10 |
Construction Complete; Connected to the National Grid, Commercial Operation started from 25th November 2012 |
|
3 |
Pikhuwa Khola |
Bhojpur |
Eastern Hydro |
2.5 |
Under Construction; Access Road construction complete. Excavation, stone soling and PCC in approach canal and desander complete. Excavation at forebay and powerhouse ongoing. Contract awarded for HM works. Bids being reviewed for EM works. TL design and cost estimation complete and bids invited for TL. |
|
4 |
Mailung Khola |
Nuwakot |
Mailung |
5 |
Under Construction; Headworks 85%, desander 25%, Powerhouse 90% complete. EM equipment ready for shipment. HR pipe fabrication 45% complete and 25% delivered to site. TL contract awarded. Excavation work at tailrace area almost (95% complete) |
|
5 |
Jhyari Khola |
Sindhu palchowk |
Electrocom |
2 |
Under Construction; 60% of headrace and penstock pipe works completed. Track opening for waterway alignment complete. About 2,000 m of headrace pipe erected. Fabrication of remaining pipe ongoing. EM equipment hasarrived in Nepal. 30% of transmission line pole erection completed. |
|
6 |
Taadi Khola |
Nuwakot |
Aadishakti |
4.2 |
Construction Completed; Testing Commensed, Commissioning soon to progress. |
|
7 |
Upper Mai |
Illam |
Mai Valley |
9.98 |
Under Construction; Camp & Housing Facilities complete. Out of 2,075m, 714 m of headrace tunnel excavation complete and excavation works ongoing. Bids received for Civil Works. Negotiation for EM and HM contracts ongoing. |
|
8 |
Tadi Khola |
Nuwakot |
Hiraratna |
5 |
Under Construction; Land acquisition towards completion. Access road and Camp Facilities construction underway. Contract documents preparation ongoing. |
|
9 |
Chotte Khola |
Gorkha |
Pashupati |
0.6 |
Under Construction; Access road construction complete. TL 95% complete. Civil works in progress. LC opened for EM. |
|
10 |
Phawa Khola |
Taplejung |
Shibani |
5 |
Under Construction; Access road 85% complete. 90% Land acquisition complete. Civil Works contract awarded. EM, HM, TL contract documents being finalised. |
|
11 |
Gelun Khola |
Sindhu palchowk |
Gelun |
3.2 |
Under Construction; Access road 90% complete, 50% Land acquisition complete. Civil, EM, HM contracts awarded, TL contract process in progress. Consortium in the process of formation. |